In a factory a wall is built flat, in a jig, by a crew that repeats the same operation forty times a day. That is an advantage only if the substrate was specified for it. The specification that wins on site — non-combustible, moisture resistant, takes a finish — says nothing about how a panel behaves when it is cut on a CNC bed, stacked six modules high in a yard, lifted from four points, and then joined to a neighbour that was built in a different jig on a different day.
This guide follows the sequence an offsite programme actually runs — layout, cutting, fixing, module joints, transport, lifting and handover — written for the people who have to close the tolerance, not the people who write the brochure.
Two Offsite Routes, Two Different Jobs for the Board
Offsite is used as one word and covers two very different products. In panelised construction, a 2D cassette — frame plus one or two skins — is fabricated and shipped flat, then erected onto a primary structure. In volumetric construction, usually called MiC, a complete room or bathroom is built as a steel-framed box with its own floor, walls, ceiling and services, and the box is the shipping unit.
The role of the board changes between the two, and so does the specification that matters. The material argument for an inorganic panel in this setting is set out in why inorganic boards fit prefab and modular builds; this page is about how the programme actually runs.
| Item | Panelised (2D cassette) | Volumetric (MiC module) |
|---|---|---|
| Board function | Structural skin on the cassette frame — takes wind and handling loads with the frame | Internal lining and partition — the steel box carries everything |
| Governing property | Flexural strength and fixing capacity | Flatness, fire class, surface readiness |
| Typical thickness | 8–12 mm single or double layer (see the thickness guide) | 8–12 mm single layer, 12 mm where impact or acoustics govern |
| Dimensional accuracy needed | Highest — the cassette is the visible module edge | High on the inner face, low on hidden faces |
| Where it fails in practice | Edge damage in the yard, screw pull-out at corners | Joint misalignment between adjacent boxes |
A fiber cement board is a non-structural panel in both cases. It contributes racking and fire performance as part of a tested assembly, but it is never the member that carries the module. Confusing the two is the first error an offsite programme makes, and it usually shows up as cracked joints after the first lift.
The Tolerance Chain: Where Modules Actually Fail
Nobody loses a programme on fire class. Programmes are lost on joints that will not close. Every offsite build carries a stack of small errors, and the only question is which layer absorbs them.
| Source of variation | Order of magnitude | Who should absorb it |
|---|---|---|
| Jig set-out and frame fabrication | 2–3 mm over a module | Frame — corrected at first-article inspection |
| Board thickness tolerance | Per the declaration of performance, typically ±0.5 mm | Board — tolerances must be declared, not assumed |
| Board moisture movement | ±0.25 % wet expansion, ≤0.15 % dry shrinkage | Joint — never the fixing |
| Crane placement of the module | 3–5 mm at the interface | Module joint — designed with cover |
| Structural movement in service | Depends on frame and height | Module joint — sealant movement capacity |
Take a 1,220 mm board and the moisture figure becomes real: 0.25 % of the width is about 3 mm. A run of six boards with the joints pulled tight has roughly 18 mm of movement looking for somewhere to go — into the surface as a crack, into the frame as a bowed stud, or into the sealant as a failed bead. The rule that prevents all three: the board is never the adjustment layer. Adjustment belongs in the module joint and in the frame shimming, because a board trimmed to fit a wrong opening telegraphs that error through the finish for the life of the building.
The Factory Sequence, With Hold Points
The order of operations in the factory decides whether the module arrives closable. This is the sequence we see work on repeat programmes.
| # | Step | What is checked before the next step starts |
|---|---|---|
| 1 | Frame set-out in the jig | Diagonal and square within agreed tolerance; stud centres set for the board module |
| 2 | Board layout drawing | Joints do not land on lifting points, corner castings, service penetrations or the module edge |
| 3 | Cutting | Cut edges square; dust extracted; edges to be exposed are sealed |
| 4 | Fixing | Screw spacing, edge distance and head depth as specified; no overdriven heads |
| 5 | Openings and penetrations | Holes cut before the finish goes on; framing behind every opening edge |
| 6 | Second layer, where specified | Joints staggered against the first layer, not aligned with it |
| 7 | Surface and decoration | Board moisture content stable; face clean and dry before any coating or decorative board is applied |
| 8 | Wrap, label, photograph | Each module photographed at the same four angles before it leaves the bay |
Step 2 is the one that is skipped. A layout drawing costs an hour; a penetration that lands on a board joint costs a rework cycle and a delivery slot. Hold two inspections beyond the in-line checks: the first article of every module type, signed off before serial production, and the pre-wrap check that the board is dry and the face clean before any coating or film goes on.
Fixing That Survives the Lift
A module is not a static object. It is lifted, set down, jacked, braced, transported over a road surface, and lifted again. Fasteners that were adequate for a wall in a building are being asked to hold a panel through a few thousand load cycles.
- Spacing. A typical specification for a 8–12 mm wall panel is 200 mm at board edges and 300 mm in the field, with an additional row at every horizontal joint. Confirm against the system certificate rather than a website.
- Edge distance. Keep fixings at least 10 mm from a cut edge and further from a module edge, where the cassette frame concentrates load.
- Head depth. The head should sit just below the surface without breaking the core. An overdriven screw is a crack initiator, and in a module it is a crack that opens during transport.
- Two layers. Stagger the joints by at least 200 mm between layers. Aligned joints in a double-layer system behave like a single joint with double the movement.
- Do not fix through the module joint. A board that spans two modules will crack the moment the crane sets the second one down.
Pull-out capacity is the number that makes the lightweight argument defensible: our boards are specified at ≥1,200 N screw withdrawal and ≥10 MPa flexural strength at 0.65–0.85 g/cm³, which is what allows a 0.85 density board — the case made in lightweight fiber cement board 0.85 — to carry a loaded shelf or a wall-hung unit without a plywood pattress. On a volumetric programme that matters twice — once for the fitting, and once because every kilogram saved in the box is a kilogram off the lifting plan.
Module Joints: Design the Gap, Then the Fire Stop
The joint between two modules is the only part of an offsite building that behaves like a site-built detail. It has to take movement, provide fire separation, and often provide weather and air control. Three types cover most programmes.
| Joint type | Where used | Board detail |
|---|---|---|
| Expressed open joint | Rainscreen facades, 10–20 mm | Board stops short of both module edges; behind it a drained and ventilated cavity |
| Sealed movement joint | Internal walls between modules | Board stops both sides; backer rod and sealant sized to the movement |
| Fire stop joint | Compartment lines, corridor walls | Mineral wool packed to full depth, A1 board closing the gap, sealant over |
Size the joint from the movement, not from what looks tidy. A sealant typically accommodates around 25 % of its joint width in movement, so a joint expected to move 4 mm needs roughly 16 mm of width — which is why a 5 mm shadow gap on a long corridor run fails in the first heating season.
For the fire stop, the material logic is the same one that applies inside the module: an A1 non-combustible board introduces no fuel, has AQ1 smoke toxicity to GB 8624, and can close the joint without adding a combustible layer at the one place where a fire would travel between compartments. The same logic governs the fire-rated partition systems inside the module. A denser calcium silicate board is the usual choice where the joint also has to take impact from trolleys or doors.
Wet Pods and Bathroom Modules
A bathroom pod is the hardest thing in an offsite programme: a small volume, high humidity, continuous service penetrations, and a finish that has to look factory-new after a sea voyage. The board is a backing, not a waterproofing layer — that distinction decides whether the pod passes its wet test.
- The board goes on the pod frame, the waterproof membrane goes over the board, and the membrane turns up at every wall-floor junction and every penetration.
- ≤0.25 % wet expansion and 30 days of immersion without delamination mean the panel will not swell the membrane off the wall. It does not mean the pod can be left without a membrane.
- Use a higher density calcium silicate board at the pod floor and behind heavy fittings, where point loads and abrasion are the governing case rather than fire.
- Where the pod is a clinical or hygiene space rather than a domestic bathroom, the same build-up is used with a coated face — see hospital and cleanroom wall cladding.
- For the visible dry faces — the wall outside the shower, the ceiling of the pod — a factory-applied decorative board removes a wet trade from the line entirely. Printed decorative wall panel faces arrive finished, which is the whole point of building in a factory.
Transport, Stacking and Sea Freight
The journey is a load case. Modules are stacked, transported and lifted, and loose board is palletised and containerised. Both need a specification, and neither is usually written down.
- Loose board, palletised: edge protection on all four corners, a waterproof wrap, and no direct contact with a concrete yard floor. Board that takes up ground moisture before it is installed will move after it is fixed.
- Sea freight: container sweating is the real risk, not rain. Desiccant in the container, board off the floor, and a wrap that keeps condensation off the face rather than trapping it against it.
- Facade cassettes: a closed cassette with a drained cavity follows the rules in external facade cladding; the module joint and the cassette joint must not coincide.
- Modules: protect finished faces with a removable film, keep lifting strops off the board, and never use the board as a bearing point for a spreader.
- Weight budget: at 0.85 g/cm³ a 12 mm board is about 10.2 kg/m² against roughly 15 kg/m² for a standard density sheet — on a module with 40 m² of lining that is a few hundred kilograms off the crane and off the shipping line.
Fire: Material Class Is Not a Module Rating
Offsite programmes produce the same conversation every time. Someone reads A1 on a data sheet and writes "1 hour fire rated module" into the specification. The two statements are unrelated.
A1 is a reaction-to-fire classification: it describes what the material contributes to a fire, and it is why the panel cannot ignite, melt or drip at 1,000 °C. Fire resistance — 30, 60, 90 or 120 minutes — is a property of a tested assembly, including the frame, the cavity fill, the fixing pattern and the joints. In our tested partition systems, 8 mm with 75 mm light steel studs and rock wool reaches one hour, 9 mm reaches two hours and 12 mm reaches three. Those are system results. They do not transfer to a module unless the module is built the way the test was built.
What to send with the module instead of a data sheet: the CE declaration of performance for the board, the classification report for reaction to fire, the test report for the assembly you actually built, and the French A+ and REACH statements for indoor air and substance compliance. The certification guide sets out what each document does and does not prove.
When Offsite Is the Wrong Answer
A guide that only lists advantages is not a guide. These cases are better solved on site, or with a different substrate.
- A very high acoustic requirement in a thin wall. Mass matters. A lightweight fiber cement board helps, but a demountable cassette at 75 mm is not a 50 dB wall — check the acoustic data before promising it.
- Curved or faceted geometry. A 6 mm board can be bent, but a curved cassette is a bespoke jig for every variant. See bending cement board for where that stops being economic.
- Refurbishment of an existing structure. Offsite wins on repetition. A one-off floor plate with unknown tolerances is a site job.
- Very small batches with bespoke decoration. Every variant of a printed decorative board is a print run and a set-up.
- Where the module has to be reconfigured after installation. Modules are fixed geometry by design; a demountable partition is the better answer.
The Sequence in One Line
Build the layout drawing before the first board, keep the board out of the tolerance chain, stop it at every module joint, protect it in the yard, and test the assembly rather than the data sheet. Programmes that do those five things do not spend their site phase repairing the factory.
If you are specifying a modular or panelised programme now, send us the wall build-up and the module joint detail — we will come back with the board, the thickness and the test report that matches it.
Frequently Asked Questions
Can fiber cement board act as the structural skin of a module?
Only within a tested assembly, never as the load-bearing member. The cassette or box frame carries the module; the board contributes racking resistance, fire performance and a fixing substrate. At 0.65 to 0.85 g/cm3 it delivers 10 MPa or better flexural strength, but it cannot span an opening on its own.
What thickness should a module partition use?
Fire strategy decides first. In our tested systems 8 mm with 75 mm steel studs and rock wool gives one hour, 9 mm two hours and 12 mm three. Where impact or acoustics govern, 12 mm is the starting point, and a denser calcium silicate board goes where point loads are heavy.
How wide should the gap be between boards at a module joint?
Wide enough to take the movement. A sealant typically accommodates about a quarter of its joint width, so a joint expected to move 4 mm needs roughly 16 mm. Boards must stop short on both sides of the joint and must never be fixed across it, or the panel will crack when the next module is set down.
Does a lighter board mean a weaker wall?
Not in the properties that matter for a lining: 10 MPa or better flexural strength and 1,200 N or better screw withdrawal still carry wall-hung units without a plywood pattress. What lightness does not buy is mass, so a high acoustic rating still needs added weight or a decoupled frame.
Can modules ship with the finish already applied?
Yes — that is the point of building offsite. Factory-applied decorative board faces arrive finished, so no wet trade enters the module, provided the board is dry and stable before coating and the face carries a removable protective film for transport.